We're currently working on building the largest ferret rescue in the United States. This section will receive updates with timestamps to let the community know how far along we are and whats happening next. This is a longstanding goal of the rescue and will help us expand our operations many times over. The new facility will need a larger staff to run so stay tuned for in-person work opportunities in the future.
March 26th, 2025
We reached out to a contractor that specifically works on veterinary medical facilities and explained our overall goal for the rescue. They were receptive and we started putting together a plan to pitch everything to the county. This initial process takes months and a great deal of care to ensure the best chance of success.
August 14th, 2025
The contractor reached out to the county and started discussions for the build. The next step from here would normally be a CIM meeting and final approvals before we break ground. Unfortunately our county wanted extra steps and a Pre-Application Screening needed to be performed.
November 3, 2025
The Pre-Application Screening passed! The county also wanted a site plan which we provided and now we're in queue for review. Once the county finishes the review they will respond with either GO or NO-GO. We're optimistic about a GO outcome based on all of the factors involved right now. If they respond with GO then we can move forward with the next planning phase.
December 21, 2025
We paid the contractor for a massive number of services so we can move forward on the project. This is going to be months of work and is around 1/4th of the overall cost of the project. All of this is paid up in full and the contractor is already working on them!
1. Project Management/Developer
2. Septic System And Well System Approval Process
3. Topographic Survey
4. Geotechnical Soil Report
5. Conceptual Site & Utility Plan
6. Conceptual Building Floor And Elevation Plans
7. Final Site Plan
8. Sepa Application & Submittal
9. Schematic Building Floor And Elevation Plans
10. Schematic M & P Plans (Mechanical & Plumbing)
11. Schematic Electrical Plans
12. Preliminary Landscape Architect Plans
13. Preliminary Parking Lighting Plans
14. Architectural Design Documents
15. Structural Engineering Preparation
16. Final Mechanical And Plumbing Plans
17. Final Electrical Plans
18. Final Civil Engineering Plans
19. Final Landscape Architect Plans
20. Final Parking Lighting Plans
21. Project Coordination
22. Agency Redlines (One Round)
23. Consultation, Meetings & Coordination
24. Electronic Autocad Data Deliverable
February 6th, 2026
A number of the surveys have now been performed including the Geotechnical Soil Report from the previous list. I know this is just a survey but it means we've technically broken ground. Kind of a huge milestone so here is a picture!